If a job requires 2500 tons of HMA over a 10-hour workday, what is the production rate needed?

Study for the NETTCP Hot Mix Asphalt (HMA) Inspector Test. Enhance your preparation with multiple choice questions, hints, and explanations. Get ready for your exam!

To calculate the production rate needed for 2500 tons of Hot Mix Asphalt (HMA) over a 10-hour workday, we can use the formula for production rate, which is the total amount of material divided by the total time taken.

In this case, you have 2500 tons and a workday of 10 hours. By dividing the total tons by the total hours, you find the following:

Production Rate = Total Tons / Total Hours = 2500 tons / 10 hours = 250 tons/hour.

This means that in order to meet the requirement of 2500 tons within the designated workday, the production rate must be 250 tons for each hour of operation. This calculation is critical for ensuring that the project stays on schedule and meets its specified output.

Other potential production rates would either fall short of or exceed what is necessary to achieve the required total in the given timeframe, thus confirming that 250 tons/hour is indeed the appropriate and precise production rate for this scenario.